Vantage Data Centers
verified· operatorFacilities
3
Total capacity
768 MW
192 live · +576 planned
Countries
1
Suppliers used
0
Energy deals
0
Commitment vs. actual
source ↗Public commitment
100%by 2030
Actual carbon-free
25%
192 MW solar / wind / hydro / geo / nuclear
Gap
+75pp
wide gap — claim far ahead of facility data
Net-zero operational (scope 1+2) by 2030; select campuses already 99%+ renewable; Climate Pledge signatory
Country reach
where they build- US3 facilities
Status mix
lifecycle of portfolio- expanding2
- operational1
Power mix
carbon-free vs fossil- grid-mixed576 MW · 75%
- Hydro192 MW · 25%
Suppliers used0
No data yet.
Facilities3
| Facility | Where | Status | Power | MW | Planned |
|---|---|---|---|---|---|
| Vantage Ashburn VA2 AI CampusAI | Ashburn, VA, US | expanding | grid-mixed | 192 | 384 |
| Vantage Quincy WA Campus | Quincy, WA, US | expanding | Hydro | — | 192 |
| Vantage Santa Clara V6 | Santa Clara, CA, US | operational | grid-mixed | — | — |