Telefónica Tech
verified· operatorFacilities
1
Total capacity
22 MW
22 live · +0 planned
Countries
1
Suppliers used
0
Energy deals
0
Commitment vs. actual
source ↗Public commitment
100%by 2030
Actual carbon-free
0%
0 MW solar / wind / hydro / geo / nuclear
Gap
+100pp
wide gap — claim far ahead of facility data
100% renewable electricity globally by 2030 (89% in 2024); net-zero by 2040 (first telco SBTi-validated)
Country reach
where they build- ES1 facility
Status mix
lifecycle of portfolio- operational1
Power mix
carbon-free vs fossil- Undisclosed22 MW · 100%
Suppliers used0
No data yet.
Facilities1
| Facility | Where | Status | Power | MW | Planned |
|---|---|---|---|---|---|
| Telefónica Alcalá Data Center | Alcalá de Henares, Madrid, ES | operational | — | 22 | — |