Applied Digital Delta Forge 1
AI dedicatedOperated by Applied Digital · Boyce, LA, US3 srcupdated 5d ago
Applied Digital's fourth AI Factory campus, a 430 MW site on more than 500 acres in Boyce, Louisiana. A 15-year take-or-pay lease with a US-based high-investment-grade hyperscaler covers 300 MW of critical IT load for approximately $7.5 billion of base-term contracted revenue. Applied Digital's fiscal Q4 2026 results, published 27 July 2026, place the campus in construction with initial operations expected in calendar 2027. The campus location was first confirmed publicly in that results release.
Compared to peers
Compared with 166 peer facilities in US.
- Capacity (MW)
- 7305×+ above median
- median 26 · p95 1,800
- Supplier coverage
- 0no peers
- median 0 · p75 0
- Announce → online lag
- in progress
- no completions yet
Bands describe deviation from peer median; not a judgment.
Ownership chain (Applied Digital)
No ownership chain tracked yet for this entity. Investigators can add parent companies via the ownership_edge table or community findings.
Public subsidies & incentives
No subsidies, tax abatements, or public incentives recorded for this facility yet.
Permits
No permits tracked for this facility yet. Public records (county permits, environmental filings, grid interconnect filings) can be sourced via community findings.
Timeline
- Announced
- —
- Groundbreak
- —
- Online
- —
- Full capacity
- —
Power
- Primary source
- grid-mixed
- Utility
- —
- PUE pledged
- —
Suppliers (0)
No suppliers tracked yet. Sign in to contribute.
Sources (3)
- filingApplied Digital Reports Fiscal Fourth Quarter 2026 Results (Form 8-K Exhibit 99.1)2026.7.27
- prApplied Digital Announces New U.S. Based High Investment-Grade Hyperscaler Tenant at Delta Forge 1, a 430 MW AI Factory Campus2026.4.23
- prCentral Louisiana Secures $3.6 Billion Applied Digital AI Factory Campus2026.5.26