Colossus — Memphis
AI dedicatedOperated by xAI · Memphis, TN, US1 srcupdated 1d ago
xAI's primary training cluster, originally 100k H100s, expanding toward 1M GPUs. Powered partly by on-site gas turbines.
Compared to peers
Compared with 117 peer facilities in US.
- Capacity (MW)
- 1,2505×+ above median
- median 32 · p95 1,560
- Supplier coverage
- 8no peers
- median 0 · p75 0
- Announce → online lag
- in progress
- no completions yet
Bands describe deviation from peer median; not a judgment.
Ownership chain (xAI)
Ownership opacity: 38 / 100 — modest3 layers traced
UBO disclosed: Elon Musk
Opacity score combines jurisdiction secrecy and chain depth (≥3 layers = +10, ≥4 = +20). Descriptive only — high opacity warrants review, not accusation.
Public subsidies & incentives
Total disclosed
$160.0M
Claimed jobs
600
$/job claimed
$267k
- Memphis-Shelby County EDGE — PILOTUS-TN · tax-abatement$80.0Mannounced 2024.7.22 · 15y term · 300 jobs claimed
- Memphis-Shelby County (community benefit fund, NOT a PILOT)US-TN · other$80.0Mannounced 2024.7.22 · 300 jobs claimed
Permits
- grid interconnectTVA / MLGWgrantedapplied 2024.5.01 · issued 2024.8.15 · 106d lag
- environmentalShelby County Health Department / TDECpendingapplied 2024.11.21 ·
- environmentalShelby County Health Department - Pollution Controlgrantedapplied 2025.1.08 · issued 2025.7.02 · 175d lag
- waterMLGW / Sand Aquifer permitpendingapplied 2025.2.19 ·
- zoningMemphis & Shelby County OPDgrantedissued 2024.6.05
- environmentalShelby County Health Department (operating without permit June 2024 - July 2025)pending
- zoningSite pre-zoned heavy-industrial; EDGE board approved 522-acre lease (no new zoning permit)granted
- waterTDEC (xAI water recycling plant operating permit)granted
Status
operational
Current capacity
250 MW
Planned capacity
1000 MW
Power source
gas
Cooling
direct-to-chip
Water draw
—
PUE
—
Capex
$18.0B
Timeline
- Announced
- —
- Groundbreak
- —
- Online
- —
- Full capacity
- —
Power
- Primary source
- gas
- Utility
- Tennessee Valley Authority
- PUE pledged
- —
Suppliers (8)
- Tesla1 srcbackup-power · Megapack BESS for Colossus 2
- VoltaGrid1 srcbackup-power · Mobile natural gas generators
- Solaris Energy Infrastructure1 srcbackup-power · On-site mobile gas turbines (~150MW)
- Memphis Light, Gas and Water1 srcelectrical · Memphis local distribution utility · local
- Mortenson1 srcgc · Construction services / data hall buildout
- NVIDIA2 srchardware · 100k H100 → expanding to 200k+ H200/GB200
- Dell Technologies1 srchardware · Server systems for Colossus expansion
- Super Micro Computer1 srchardware · Liquid-cooled GPU server systems
Sources (1)
- operatorhttps://x.ai/blog/colossus