[J] MEEDOEN

Meta Luleå Data Center

Operated by Meta · Luleå, Norrbotten, SE1 srcupdated 3mo ago

https://datacenters.atmeta.com/lulea/

Meta's first European data center, uses outside-air cooling and hydropower.

Compared to peers

Compared with 7 peer facilities in SE.

Current capacity
120 MWno peers
median 0 · p95 25
Supplier coverage
2no peers
median 0 · p75 1
Announce → online lag
in progress
no completions yet

Bands compare operating capacity with the peer median. Planned capacity is shown separately and is not added.

Ownership chain (Meta)

No ownership chain tracked yet for this entity. Investigators can add parent companies via the ownership_edge table or community findings.

Public subsidies & incentives

Total disclosed
$30.0M
Claimed jobs
300
$/job claimed
$100k
  • Norrbotten Region / Luleå Kommun / VattenfallSE · infrastructure
    $30.0M
    announced 2011.10.27 · 10y term · 150 jobs claimed
  • Norrbotten Region / Luleå Kommun / Vattenfall (PPA + infra)SE · infrastructure
    announced 2011.10.27 · 10y term · 150 jobs claimed

Permits

  • environmentalNorrbotten County Administrative Board
    granted
    issued 2012.4.26
  • environmentalNorrbotten County Administrative Board (Länsstyrelsen)
    granted
Status
operational
Current capacity
120 MW
Planned capacity
—
Power source
hydro
Cooling
air
Water draw
—
PUE
—
Capex
$1.5B

Location

City
Luleå
Region
Norrbotten
Country
SE
Coordinates
65.5848, 22.1547
View on OpenStreetMap →

Timeline

Announced
—
Groundbreak
—
Online
—
Full capacity
—

Power

Primary source
hydro
Utility
—
PUE pledged
—

Suppliers (2)

  • Vattenfall1 src
    electrical · Hydroelectric utility · local
  • Skanska1 src
    gc · Construction Luleå Node Pole · local

Sources (1)

Community findings (0)

No findings submitted yet. Sign in to dispute or correct facts.